Maintenance of cutting head, Cleaning procedures, Remove the cutting head ( caution: sharp blades ) – Paragon 6133410 (120v) THE COOLER User Manual
Page 5: Cutting head blade replacement, Installing the cutting head
Cleaning Procedures
1. Remove all ice from the ice horn and storage compartment.
2. Operate the motor for several minutes to remove any water collection on the cutter head.
3. Turn off the POWER switch. (Not used on all models.)
4. Unplug the power cord from the electrical outlet.
5. Using a clean cloth, wipe down the following items.
• The inner surface of the ice horn (Caution: Sharp Blades)
• The outside surface of the ice horn casting.
• The ice pusher.
• All interior and exterior surfaces.
6. To clean the water collection tray.
• Tilt tray to drain the water trapped in the drain cavity.
• Slip the drain hose off the nipple fitting.
• Lift the tray out of the cabinet
• Clean tray and area below tray with clean cloth.
Note: FDA approved cleaners may be used when required for sanitation. Do not use ammonia
based cleaners on polycarbonate door and/or side panels.
BLADES ARE SHARP AND OPERATE AT HIGH SPEEDS! Please be sure to keep all body parts and any
objects such as picks or scoops away from the ice horn while POWER is on!
MAINTENANCE OF CUTTING HEAD
Remove the Cutting Head (Caution: Sharp Blades)
1. Turn off the POWER switch. (Not used on all models.)
2. Unplug the power cord from the electrical outlet.
3. Rotate the cutting head until the set-screws are accessible through the discharge opening located
inside the top panel of the storage cabinet.
4. Use a 1/8” hex wrench to loosen the set-screws.
5. Slide the cutting head off the motor shaft and remove the cutting head out of the top side, inlet, of the
ice horn.
Cutting head blade replacement
1. Remove the two screws per blade.
2. Lift the old blades out.
3. Position the new blades on the head with the cutting edge extending between 1/32” to 1/16” out from
the cutting head surface. This setting will control the granular size of the ice.
4. Use the blade screws to secure the blades to the head.
Installing the Cutting Head
1. Slide the cutting head down into the ice horn with the coupler end first.
2. As the cutting head is slipped onto the motor shaft, align the set screws to the flat location of the motor
shaft.
3. Tighten the setscrews with a 1/8” hex wrench.
4. Spin cutting head by hand to insure clearance with horn.
5. Machine is now ready for use.
5