6. Loosely attach the Stack Mounting Bracket to the front of the truck bed
using the 3/8” hardware supplied. Set the Stack up in the bed and loosely 
attach it to the Stack Mounting Bracket. Make sure the Stack is vertical 
and in the desired position. Refer to Figure 3. 
 
 
 
 
7. Confirm the base of the Stack is resting in the same position as in Step 4.
Re-trace and center punch if needed. This is where the 18” Extension 
Pipe will pass through the floor. Remove the Stack from the bed of the 
truck. Drill the hole using a 5” saw. It may be required to cut a part of a bed 
floor rail away. Refer to Figure 4. 
 
 
 
 
 
8. Measure from the 18” Extension Pipe slip joint to the Extension Pipe.
Mark and cut the shorter side of the 20” Elbow to the required length so 
that it lines up with the Extension Pipe. Cut the Extension Pipe in a place 
where the Flex Pipe can be placed between the Extension Pipe and the 
20” Elbow. It may be necessary to cut the 20” Elbow again as well as the 
Flex Pipe to ensure proper fit. Refer to Figure 5. 
 
 
 
 
9. Attach the 20” Elbow to the 18” Extension Pipe slip joint and then attach
the Flex Pipe to both the 20” Elbow and the Extension Pipe. Be sure to 
slide the required Clamps over the 20” Elbow and Flex Pipe before 
connecting it to the Extension Pipe. Refer to Figure 6. 
 
 
 
 
 
 
 
 
 
 
 
 
Figure3
Figure 4
Figure 5
Figure 6