beautypg.com

KROHNE BM 100A ATEX EN User Manual

Page 12

background image

Section 4 – Initial start-up / Section 5 - Operation

BM 100 A ATEX

10/2001

12

,QLWLDOVWDUWXS

Disconnect from power before starting work!

Check the following points before device start-up:

Do probe, flange and gaskets have adequate corrosion resistance to the tank product?

Do the data on the signal converter nameplate agree with your operating data?

Check that the measuring device has been properly installed on the tank.

Is the equipotential bonding system correctly connected?

Are supply power and I/O functions correctly connected?

Are the covers of the terminal and electronics compartments firmly in place?

Have the special cover locks been tightened down?

Further start-up procedures are described in the standard Installation and Operating Instructions
for the BM 100 A.

2SHUDWLRQ

In a potentially explosive atmosphere you can parametrize the device with the aid of the supplied
bar magnet (control via magnetic sensors without opening the housing) or digitally via the signal
output.

Do not open the covers of terminal compartment and electronics compartment while
operating in a potentially explosive atmosphere.