3. Complete all mechanical removal and replacement, then locate
and mount the boxes (SSCs or Junction Boxes) to the box-
mounting-bars.
4. Re-connect or make new ground straps that are needed for a
proper installation.
5. Ensure all load cells are plumb and properly 'loaded', then
loosen and set the checking to proper gap, 1/32" - 1/16".
6. Leave a 'drip-loop' in the cable at the cell and at the box entry.
8/04
3
50651 Issue # 2
Cup Anti-Rotation Pin
Load Cell
Anti-rotation Pins