CB Series Startup Form
Date:______________
Job Name:_____________________________________________________________________
Address:______________________________________________________________________
Model Number:_________________________________________________________________
______________________________________________________________________________
Serial Number:_____________________________________________ Tag:_______________
Startup Contractor:______________________________________________________________
Address:__________________________________________________
_________________________________________________________
Phone:_____________
Pre Startup Checklist
Installing contractor should verify the following items.
1. Is there any visible shipping damage?
Yes
No
2. Is the unit level?
Yes
No
3. Are the unit clearances adequate for service and operation?
Yes
No
4. Do all access doors open freely and are the handles operational?
Yes
No
5. Have all shipping braces been removed?
Yes
No
6. Have all electrical connections been tested for tightness?
Yes
No
7. Does the electrical service correspond to the unit nameplate?
Yes
No
8. On 208/230V units, has transformer tap been checked?
Yes
No
9. Has overcurrent protection been installed to match the unit nameplate
requirement?
Yes
No
10. Have all set screws on the fans been tightened?
Yes
No
11. Do all fans and pumps rotate freely?
Yes
No
12. Is all copper tubing isolated so that it does not rub?
Yes
No
Ambient Temperature
Ambient Dry Bulb Temperature ________°F
Ambient Wet Bulb Temperature ________°F
Refrigeration System 1 - Cooling Mode
Pressure
Saturated
Temperature
Line
Temperature
Sub-cooling
Superheat
Discharge
Suction
Liquid