Commissioning and decommissioning
6.1.1 Checking the rotation direction
The intended direction of rotation of the drive
shaft is shown by the rotary direction arrow
(Fig. 4/O).
a) Start the motor briefl y (max. two seconds) to
check the direction of rotation. To see the direc-
tion of rotation using the aperture (Fig. 4/D). For
this the fi lter housing (Fig. 2/h
1
) must be remo-
ved. Remove clips (Fig. 2/y
1
), remove fi lter cover
(Fig. 2/e
1
) complete with fi lter housing (Fig. 2/h
1
).
When looking at the impeller, it must rotate clo-
ckwise.
NOTICE
Incorrect direction of rotation
Running in reverse for a long time may damage the
machine.
Use a phase sequence indicator to check the direc-
tion of rotation (anti-clockwise rotating fi eld).
6.2 Decommissioning/
storing
Stop the machine
a) Switch the machine off.
b) If available close the cut off device in the suction
pipe.
c) Disconnect the machine from the electricity
source.
d) Depressurise the machine: Open the pipes
slowly.
The pressure reduces slowly.
e) Remove the pipes and hoses.
f) Seal the connections for suction nozzles using
adhesive foil.
see also Section 3.2.1, Page 11
6.3 Re-commissioning
a) Check the condition of the machine (cleanliness,
cabling etc.).
For installation see Section 5 Page 14
For commissioning see Section 6.1 Page 16