Connection cable, Accuracy of the ids measuring technique, Commissioning, measuring, calibration – Xylem Sentix F 900-3 User Manual
Page 4

Commissioning, measuring, calibration
SenTix
12
ba75844e02
04/2010
Shaft dimensions, material, electrical connection
Connection cable
Accuracy of the IDS measuring technique
Commissioning, measuring, calibration
Commissioning
Prepare the electrode for measuring as follows:
z
Remove the watering cap from the electrode tip. Possible salt deposits in
the area of the watering cap do not affect the measuring characteristics
and can easily be removed with deionized water.
Note
Please keep the watering cap. It is required for the electrode to be stored.
Always keep the watering cap clean.
z
Remove any gas bubbles behind the pH membrane by shaking.
z
Connect the electrode to the meter.
z
Calibrate the electrode according to the operating manual of the meter
and observe the following rules while doing so:
WTW model
Shaft
Electrical connection
Length
[mm]
Ø
[mm]
Material
Combination
electrode
connection
Meter con-
nection
Cable
length
SenTix
®
940
120
12
PPE/PS
Fixed cable
Digital plug
1.5 m
SenTix
®
940-3
120
12
PPE/PS
Fixed cable
Digital plug
3 m
SenTix
®
F 900
120
12
COC
Fixed cable
Digital plug
1.5 m
SenTix
®
F 900-3
120
12
COC
Fixed cable
Digital plug
3 m
Diameter
4.3 mm
Smallest allowed
bend radius
Fixed installation:
20 mm
Flexible use:
60 mm
Plug type
Socket, 4 pins
Measured parameter
Accuracy (± 1 digit)
pH
± 0,004
U [mV]
± 0,2
T [°C]
± 0,1