2. Installation

22

PNEG-1614 Heavy Duty Bin Stairs and Platform Assembly for 2.66" Corrugated Bin

5.

Figure 2AB

shows the addition of the steps. Three (3) steps will be located above the rest platform

and four (4) are located below the rest platform. The first step above the platform will need to be
securely attached to the handrail and toe plate. A field drilled 3/8" hole will need to be placed in the
handrail in line with the slot in the step. Self-tapping screws will need to be placed in the top of the
step for connection to the toe plate.

Figure 2AB

6. Next, the handrail posts can be attached as shown

in Pages 17-19

of the manual. NOTE: The

handrail for the stair section above the rest platform will need to be cut to length. A hole will have
to be drilled in the handrail to attach to the handrail post. It can be attached in the same way as
previous discussed in the manual.