beautypg.com

Grain Systems Bin Flooring PNEG-222 User Manual

Page 9

background image

2. Recommended Method for Full Floor Installation

PNEG-222 48' Cor-Lok and Cut-Lok Flooring

9

Figure 2C

4. Install flooring starting at the bin wall on the opposite side of the unload auger. Floor planks should be

placed perpendicular to the unload auger with the outside edge the correct distance from the center
of the bin.

(See Figure 7A on Page 17.)

Be sure the flat edge of the floor plank is facing the bin wall

and the open channel edge is facing towards the center of the bin.

(See Figure 2C.)

Position the

supports for the first/shortest floor plank according to the number of bin rings and corrugation as
shown in the illustrations

on Pages 20-30

or stated in the charts

on Pages 31-32

. Attach the flashing

to flooring and bin wall to hold plank in place. (

See Page 14

for flashing installation.)

5. POSITION THE NEXT ROW OF SUPPORTS ACCORDING TO THE CHALK LINES

and support

layout. The straight tab should “snap” under the first (previous) floor piece. After the supports in the
row are correctly positioned, install the next floor piece by hooking the open channel edge under the
outside hooks of the floor supports. Push down sharply on the edge of the floor piece until it snaps
into the previous floor piece.

(See Figure 2C.)

Continue this process for the rest of the floor cutting

planks for center and intermediate wells as needed.

See Figure 5A on Page 15

for center well

support locations.

NOTE: Whenever there is more than Dimension “B” divided by three inches (B/3") of plank unsupported

beside the bin wall, there should be a support on that plank or a support on each of the
planks adjacent to it such that no more than Dimension “B” divided by three inches (B/3") is
unsupported. For example: 2.66" bin with 8 rings has a “B” dimension of 22". Take 22"/3" = 7.33"
(Round to 7"). Therefore, there should be no more than 7" of unsupported floor plank.

IMPORTANT: First piece of flooring must start at the
proper distance from centerline of bin. Refer to floor
layout

on Page 17

. First piece may need to be

trimmed for length to fit at the proper location.