5. Overview
Refer to the drawing on page 2 of this manual.
# Description
# Description
1 Centre
leg
14 Pulley
2 Outer
leg
15 Retaining hook
3
Caster (with brake)
16 Winch wheel
4 Sliding
yoke
17 Winding drum and brake assembly
5 Positioning
arm
18 Brake lever with spring
6 Backstop
19 Winch wheel handle
7
Main vertical frame
20 Load cradle
8
Telescopic section – inner part
21 Extendable arm with protective caps
9
Telescopic section – outer part
22 Extendable arm pin lock
10 Winch
assembly
23 Cradle mounting head with tilt latch
11 Slide
bar
24 Crossbar with protective caps
12 Slide bar lock
25 Hook for panel support
13 Steel
cable
6. Assembly
The drywall lift is composed of 3 main parts:
o
Tripod base assembly
o
Vertical frame assembly
o
Cradle assembly
Tripod base
Mount the casters [3] in the tripod base.
Place the base on its casters [3] and lower the backstop [6].
Press and hold the ring of the yoke [4] down while unfolding the two outer legs [2], until the
yoke pin snaps into the locking hole near the centre of the tripod.
Figure 1
Vertical frame
Install the vertical frame [7] in the V-shaped angles on the tripod base. Make sure the frame is
pushed all the way down.
Attach the handle [19] to the winch wheel [16].
Move the winch assembly [10] into working position by holding the wheel [16] and brake
handle [18] as shown in figure 2. Push the brake handle all the way up while rotating the wheel
slightly forward, grab the winch arm and secure the brake handle with your thumb to prevent
backlash (figure 3).