19

4 Mounting

VEGAPULS 63 • Foundation Fieldbus

36514-EN-130228

0%

100%

1

2

3

4

5

6

7

8

10

9

Fig. 14: Configuration surge pipe
1 Radar sensor

2 Marking of the polarisation direction

3 Thread or flange on the instrument

4 Vent hole

5 Holes

6 Weld joint

7 Welding neck flange

8 Ball valve with complete opening

9 Fastening of the surge pipe

Instructions for orientation:

Note marking of the polarisation plane on the sensor

With threaded fitting, the marking is on the hexagon, with flange

connection between the two flange holes

All holes in the surge pipe must be in one plane with this marking

Instructions for the measurement:

The 100 % point must be below the upper vent hole

The 0 % point is the end of the surge pipe

For the parameter adjustment, select "Application standpipe" and

enter the tube diameter to compensate errors due to running time

shift

A false signal suppression with integrated sensor is recommended

but not mandatory

The measurement through a ball valve with complete run is pos-

sible