Project Name / Date

Division 23 52 33.13 - 5

B. Manufacturer’s representative to verify proper and complete installation.

3.2 START-UP

A. Shall be performed by Raypak factory-trained personnel.

B. Test during operation and adjust if necessary:

1. Safeties (2.2 - F)
2. Operating

Controls

(2.3)

3. Static and full load gas supply pressure
4. Gas manifold and blower air pressure

C. Submit copy of start-up report to Architect and Engineer.

3.3 TRAINING

A. Provide

factory-authorized

service representative to train maintenance personnel on procedures

and schedules related to start-up, shut-down, trouble shooting, servicing, and preventive
maintenance.

B. Schedule training at least seven days in advance.

END OF SECTION