Temperature Controller Installation

Follow the procedure below to install MC-91 or
MCC-91 temperature controllers.

Do not attempt to connect the temperature controllers with the power on. There is 120
volt potential, next to the temperature controller connections inside the unit.

Do not connect the temperature controller to the 120VAC terminals provided for
the optional solenoid drain valves.

All service and wiring should be performed by a registered installer.

WARNING

Outline of Temperature controller

securing screw

1-21/32"

3-5/16"

securing screw

wiring hole

Mounting on the wall

1. Determine a suitable location for the

controller.

2. Make three holes in the wall as shown.

3. Run the cable between the controller and the

Rinnai water heater or the controller and
another controller.

4. Remove the face plate from the temperature

controller using a screw driver.

5. Connect the cable to the temperature controller.

6. Mount the controller to the wall using the

holes drilled in step 2.

7. Disconnect the power from the Rinnai water

heater.

8. Remove the cover of the Rinnai water heater.

9. Remove the plastic cover from the PCB and

electrical connections.

10. Thread the cable through the access hole at

the base of the unit and connect the wires to
the controller terminals on the right hand side
bottom of the PCB.

11. Secure the controller cable using the clamp

provided.

12. Replace plastic cover over PCB and then

replace the cover of the Rinnai water heater.

CABLE CLAMP

TEMPERATURE
CONTROL CABLE

TEMPERATURE CONTROL
CONNECTION TERMINALS