Project Name / Date
4. Canada only: CAN/CGA B149 Installation Code and CSA C22.1 CEC Part I
5. Manufacturer’s installation instructions, including required service clearances and venting
guidelines
B. Manufacturer’s representative to verify proper and complete installation.
3.2 START-UP
A. Shall be performed by Raypak factory-trained personnel.
B. Test during operation and adjust if necessary:
1. Safeties
2. Operating
Controls
3. Static and full load gas supply pressure
4. Gas manifold and blower air pressure
5. Amp draw of blower
6. Combustion
analysis
C. Submit copy of start-up report to Architect and Engineer.
3.3 TRAINING
A. Provide
factory-authorized
service representative to train maintenance personnel on procedures
and schedules related to start-up, shut-down, troubleshooting, servicing, and preventive
maintenance.
B. Schedule training at least seven days in advance.
END OF SECTION