20. Hold the demand valve subassembly in place and install the Inlet Fitting. Hand tighten (approximately

40 in lbs). As the Inlet Fitting is installed the Demand Lever position will change and it will be loosely

retained until the final adjustment is made.

21. Use the nut driver to tighten the Lock Nut until the Demand Lever rises to be level with the top of

the Housing.

22. Install the LP Hose (19) onto the Inlet Fitting. Be certain to secure the Inlet Fitting with a wrench as the

hose fitting is tightened (40 in-lbs).

23. Attach the LP Hose to the first stage regulator and torque to 40 in lbs.

24. The Dual Octo is designed to be compatible with regulators that operate with an intermediate pressure

ranging from 120 to 150 PSI. If the first stage is not operating within these pressures, the Dual Octo

may not perform properly. If necessary, service the first stage regulator so that it operates within these

pressures or match the Dual Octo to a first stage that does operate within the prescribed limits.

25. Apply pressure to the regulator assembly and tighten the Lock Nut until a very slight leak is presented.

Loosen the Lock Nut slowly until the leakage stops. Continue loosening approximately 1/8 turn. The

Demand Lever should be aligned with or slightly below the surface of the top of the Housing and should

allow slight movement of the lever without opening the valve. If the correct alignment is not present

continue loosening the Lock Nut until alignment is achieved, but do not loosen the Lock Nut more than

1/4 turn past the point where leakage is stopped. If alignment cannot be achieved it is likely the Demand

Lever is distorted and must be replaced.

26. Install o-ring (14) on to the Mouthpiece Boss.

27. Install the Mouthpiece Boss into the Housing noting the desired orientation of the Mouthpiece. There

are two positions available and the selection should match the user’s choice. Use snap ring pliers to

spread the Retaining Ring (15) and position it over the groove on the Mouthpiece Boss. After the

Retaining Ring is released, check to verify that it contained in the groove. Pull on the Mouthpiece Boss to

check retention.

28. Install the Mouthpiece (12) and secure with the Mouthpiece Strap (13).

29. Install the Diaphragm, Retainer and Purge Cover with the Sherwood logo aligned parallel with the axis

of the Inlet Fitting.

CAUTION – Rotation of the Inlet Fitting within the Housing will damage the

indexing feature and may cause the Demand Lever to misalign. This could

compromise regulator performance and will require replacement of the Housing.

WARNING – Failure to properly secure the Mouthpiece Boss to the Housing may

result in separation during a dive. If this were to occur the diver may be exposed

to inhalation of water causing a potentially hazardous condition requiring an

appropriate emergency response to avoid serious injury or death.