Installation manual of room air conditioner – haier AF122XCEAA User Manual

Page 15

background image

13

2.Piping cutting and flaring

Be sure to carry out deburring after cutting with a pipe cutter.
Insert flaring tool to make a flare.

Installation inspection and test run:

Please operate unit according to this Manual.

Items to be checked during test run. Please made a '' '' in '' ''

Are there any gas leakage?

How is insulation at piping connection carried out?

Are electric wires of indoor and outdoor unit firmly inserted into terminal block?

Is electric wiring of indoor and outdoor securely fixed?

Is drainage securely carried out?

Is earth line(grounding) securely connected?

Is power supply voltage abided by the code?

Is there any noise?

Is control display normal?

Is cooling operation normal?

Is room temp. regulator normal?

Liquid pipe

Pipe diameter

Size A (mm)

0.8 ~1.5

1.0 ~1.5

6.35mm(1/4")

9.52mm(3/8")

Gas pipe

A

Correct

Incorrect

Lean Damage of flare

Crack

Partial

Too outside

Flare tooling die

Others

The power plug should be connected as follows: L for live line, N for neutral line and
for

grounding.

Voltage: single-phase1PH,220-230V*,50Hz

The power source must be grounded.

Connection parameters: H05RN-F 3G(1.0-1.5)mm

Signal parameters:

1.Power supply requirements:

Cables for power supply, connection and signals are prepared by the owner.

Electrical cables should be connected by ìYî method. Damaged or wornelectrical cable
must be replaced by authorized after sales agents.

A circuit breaker must be installed

Dedicated electrical cable should be installed by a qualified technician in
accordance with the state regulation for electrical engineering.

H05RN-F 2x(0.75-1.5)mm (Shieded wire)

Installation Manual of Room Air Conditioner

The signal wire must be shielded wire.