beautypg.com

Activeforever Global Lift Commercial Series Portable Lift 450 User Manual

Page 8

background image

Step 6: Place the Anchor Plate in the area, make sure that the front of the Anchor

Plate is 11” to 16” from the water’s edge and that the decal’s arrow on the anchor

plate is pointing to the water’s edge (refer to overview). A key element is to make

sure that the Anchor Plate is level and square with the pool so that your Commercial

Series Lift sits properly on the deck.

Step 7: Bonding the unit – The bonding lug is included with the Anchor plate

(furthest point from the pool wall on the Anchor Plate) locate the bonding lug,

connect the bonding lug to the bonding grid.
NOTE: Make sure all local codes and ordinances are met.

Step 8: Pour in your concrete, (make sure you cover the holes in the 3 threaded

anchor’s so you don’t get concrete in the threads) minimum of 4,000 psi with

reinforcing rod. Also make sure that the tops of the threaded anchors are flush with

the deck. Before you install your lift make sure you let the concrete set up for 48

hours.

Step 9: After the concrete has set for 48 hours, now it’s time to install your lift. Place

your Commercial Series Lift over the anchor holes, screw in the Anchor bolts that are

included and tighten down securely. Once you have completed the installation, please

refer to User’s Manual for a safe operation.

www.ActiveForever.com