Apogee fln set-up, Caution – Yaskawa APOGEE FLN User Manual
Page 8

YASKAWA TOEP YAICOM 10A Z1000 Bypass Network Protocol Apogee FLN Technical Manual
8
APOGEE FLN Set-Up
A Yaskawa America, Inc. representative is responsible for proper configuration of the Bypass for its primary application, while a Siemens
Building Technologies, Inc. representative is responsible for field panel programming to make use of the Bypass functionality in the
building automation system. As such, there must be coordination between the Yaskawa America and Siemens Building Technologies
representatives to ensure that the programming of the drive is consistent with the particular application requirements. After verifying that
the drive installation and wiring are correct, apply power to the drive. Table 1.1 below lists the parameters and their values required for
proper APOGEE FLN communication and control.
Z1000 Bypass Parameter Settings for APOGEE FLN Communications
Table 1.1 - Drive Communication Parameter Settings
Parameter Number
Digital Operator Display
Settings for APOGEE FLN Communication
Z1-07
Reference Source
2: Serial Com
Z1-08
Run Source
2: Serial Com
Z3-02
Serial Comm Adr
Select the Bypass address
Z3-03
Serial Baud Rate
2: 4800 Baud
Z3-01
Protocol Select
2: P1
CAUTION
A Yaskawa representative should set the drive parameters to their appropriate values. Changes made
to the parameters other than what is listed in the table above can result in damaging the drive or
building equipment.
Programming The Z1000 Bypass For APOGEE FLN
Refer to the Z1000 Bypass User Manual, SIEPYAIZ1B01, for detailed information on using the Z1000 Operator.