beautypg.com

Installation – Desa CCL3924PRA User Manual

Page 13

background image

www.desatech.com

111161-01H

13

For propane/LP units, the installer must supply

an external regulator. The external regulator will

reduce incoming gas pressure. You must reduce

incoming gas pressure to between 11" and 14" of

water. If you do not reduce incoming gas pres-

sure, heater regulator damage could occur. Install

external regulator with the vent pointing down

as shown in Figure 13. Pointing the vent down

protects it from freezing rain or sleet.

CAUTION: Use only new,

black iron or steel pipe. Inter-

nally-tinned copper tubing may

be used in certain areas. Check

your local codes. Use pipe of

1/2" diameter or greater to allow

proper gas volume to heater. If

pipe is too small, undue loss of

volume will occur.

Installation must include an equipment shutoff

valve, union and plugged 1/8" NPT tap. Locate

NPT tap within reach for test gauge hook up. NPT

tap must be upstream from heater (see Figure 14,

page 14).
IMPORTANT:

Install equipment shutoff valve

in an accessible location. The equipment shutoff

valve is for turning on or shutting off the gas to

the appliance.

Check your building codes for any special re-

quirements for locating equipment shutoff valve

to fireplaces.

Apply pipe joint sealant lightly to male NPT

threads. This will prevent excess sealant from

going into pipe. Excess sealant in pipe could result

in clogged heater valves.

INSTALLATION

Continued

CONNECTING TO GAS SUPPLy

WARNING: This appliance

requires a 1/2" NPT (National

Pipe Thread) inlet connection to

the pressure regulator.

WARNING: A qualified ser-

vice person must connect heater

to gas supply. Follow all local

codes.

CAUTION: Never connect

propane/LP heater directly to the

propane/LP supply. This heater

requires an external regulator

(not supplied). Install the exter-

nal regulator between the heater

and propane/LP supply.

WARNING: Never connect

natural gas heater to private

(non-utility) gas wells. This

gas is commonly known as

wellhead gas.

Installation Items Needed

Before installing heater, make sure you have the

items listed below.

• piping (check local codes)

• sealant (resistant to propane/LP gas)

• equipment shutoff valve *

• test gauge connection *

• sediment trap

• tee joint

• pipe wrench

* A CSA design-certified equipment shutoff valve

with 1/8" NPT tap is an acceptable alternative to

test gauge connection. Purchase the optional CSA

design-certified equipment shutoff valve from your

dealer. See Accessories, page 34.

Figure 13 - External Regulator With Vent

Pointing Down

Propane/LP
Supply Tank

External
Regulator

Vent
Pointing
Down

This manual is related to the following products: