beautypg.com

For plan 13, 3piping recommendations – Flowserve Uniseal Series BW Seals User Manual

Page 5

background image

For Plans 11, 21 and 32:

Shaft Rotation

Inlet

Plugged

(from exposed end of gland)

Port

Clockwise (CW)

Port b

Port a

Counterclockwise (CCW)

Port a

Port b

For Plan 13:

Shaft Rotation

Outlet

Plugged

(from exposed end of gland)

Port

Clockwise (CW)

Port a

Port b

Counterclockwise (CCW)

Port b

Port a

5

3

Piping Recommendations

3.1 Install and maintain an adequate piping plan. The Uniseal requires a

clean, cool environment for maximum seal life. Typical piping plans are

listed below. Contact Flowserve for additional piping plan information or

technical support.
Plan 11: default inner seal flush from pump discharge on horizontal

pumps

(single

seals)

Plan 13: default inner seal flush and vent from pump suction on

vertical pumps (single seals)

Plan 21: inner seal flush from pump discharge through a cooler for use

with hot products (single seals)

Plan 32: inner seal clean external flush for use with abrasive products

or products that are incompatible with the seal (single seals)

Plan 52: dual seal circulation through a low pressure reservoir

(dual

seals)

Plan 53: dual seal circulation through a pressurized reservoir

(53A), finned tube array (53B) or

piston

accumulator

(53C) (dual seals)

CW

Rotation

F

D

F

Q

CCW

Rotation

a

b

Plan 62: external quench on

atmospheric side of

seal (single seals)

3.2 For

single seals, follow the port

connections listed below, see

Figure 6. Quench and Drain

ports on single seals should be
plugged if not used

as a good

housekeeping practice.

Single seal port connections

Figure 6