3 Pump Preparation

3.1 Check the condition of the bearing assembly and axial shaft

movement.

3.1.1 Check radial shaft movement with a dial indicator by forcing

the shaft up and down and observe the movement of the

dial indicator. Replace or repair bearing assembly if the

movement is greater than the manufacturer's specifications

or 0.381 mm (0.015 inch).

3.1.2 Shaft run-out should be less than 0.127 mm (0.005 inch).

Turn the shaft 360 degrees and observe the movement

of the dial indicator. See Figure 1.

Radial Shaft Movement

Figure 1

0.381 mm

(0.015 inch)

Maximum

Axial Shaft Movement

Figure 2

3.1.3 Axial shaft movement must be less than 0.381 mm

(0.015 inch). Adjust the bearing cover shim thickness

according to the manufacturer's instructions. If spring

loaded spherical thrust bearings are utilized, it may be

necessary to machine the gasket surface of the bearing

cover in lieu of adding shims. See Figure 2.

0.381 mm

(0.015 inch)

Maximum