Program
1. Connect the unit to the digital voltmeter as shown in
Figure 4.1
. See also
“Calibration Setup” on page 48
, step 4.
2. Program the output to 5% of full scale voltage by sending the following
command string from the computer:
VSET2;ISET25 (for 1kW Model 40-25)
3. Adjust voltage programming offset potentiometer R28 (VOFF) until the external
meter reading is within the power supply's voltage program accuracy
specification. Refer to specification tables in
Section 1
.
Example: ±75mV ±(0.3% (5% of 40V)) (for 1kW Model 40-25)
4. Program the output to full scale voltage by sending:
VSET40;ISET25 (for 1kW Model 40-25)
5. Adjust voltage programming full scale potentiometer R51 (VADJ) until the
external meter reading is within the power supply's voltage program accuracy
specification. Refer to specification tables in
Section 1
.
Example: ±75mV ±(0.3% of 40V) (for 1kW Model 40-25)
6. Repeat steps 2 to 5 (between VOFF and VADJ) for best linearity.