FIREPLACE INSTALLATION

Continued

FIREPLACE INSTALLATION

Checking Gas Connections (Cont.)
Installing Optional Wall Mount Switch - GWMS2

Test Pressures Equal To or Less Than 1/2 PSIG (3.5 kPa)

1.

Close equipment shutoff valve (see Figure 33).

2.

Pressurize supply piping system by either opening propane/LP
supply tank valve for propane/LP gas fireplace or opening main
gas valve located on or near gas meter for natural gas fire-
place, or using compressed air.

3.

Check all joints from propane/LP supply tank or gas meter to
equipment shutoff valve (see Figure 34 for propane/LP or Figure
35 for natural gas). Apply noncorrosive leak detection fluid to all
joints. Bubbles forming show a leak. Correct all leaks at once.

Figure 33 - Equipment Shutoff Valve

Open

Closed

Equipment
Shutoff
Valve

Figure 35 - Checking Gas Joints for Natural Gas Fireplace

Figure 34 - Checking Gas Joints for Propane/LP Gas Fireplace

Propane/LP
Supply Tank

Gas Valve

Equipment
Shutoff
Valve

Gas
Meter

Gas Valve

Equipment
Shutoff
Valve

Pressure Testing Fireplace Gas Connections

1.

Open equipment shutoff valve (see Figure 33).

2.

Open propane/LP supply tank valve for propane/LP fireplace or main
gas valve located on or near gas meter for natural gas fireplace.

3.

Make sure control knob of fireplace is in the OFF position.

4.

Check all joints from equipment shutoff valve to gas valve
(see Figure 34 for propane/LP or Figure 35 for natural gas).
Apply noncorrosive leak detection fluid to all joints. Bubbles
forming show a leak. Correct all leaks at once.

5.

Light fireplace (see Operating Fireplace, pages 24 through 26).
Check all other internal joints for leaks.

6.

Turn off fireplace (see To Turn Off Gas to Appliance, page 24).

Figure 36 - Connecting Wall Swith to Control Valve

INSTALLING OPTIONAL WALL MOUNT
SWITCH - GWMS2

1.

Connect one terminal of 25 ft. wire for the wall switch to the
TPTH terminal on the valve. Connect remaining wire terminal
to the TH terminal on the valve. Make sure that the wire termi-
nals are in the positions on the unit as pictured in Figure 36. If
wires are not connected as shown the switch will not work.

2.

Route the 25 ft. wire through openings provided on the sides of
the burner system to a convenient location to mount your switch.

3.

Connect one bare wire end to each of the terminals of the
GWMS2 wall switch.

4.

Install the wall switch and cover in the wall.

To Wall Switch