Commissioning check list, General, Unit – ducted heating – Bonaire 3 Star Mid Efficiency User Manual
Page 11: Ductwork, Site, Customer hand over, Ommissioning, Heck, Commission check list

3
S
TAR
M
ID
E
FFICIENCY
D
UCTED
G
AS
H
EATER
.
Page 11
Commission Check List
Commissioning Check List
G
ENERAL
All equipment ordered by the customer is installed.
The unit is level and secure.
The mains and control wiring are complete and the circuit breaker and GPO are turned ON.
All Controller functions for the appliance operate.
All electrical or gas connections are to manufacturers specifications and the relevant electrical
or gas standards and codes.
U
NIT
–
D
UCTED
H
EATING
Electrical polarity of the power outlet is correct.
Heater is installed away from sources of dust and fumes (ie. pool chlorine/petrol etc).
Gas leaks checked for, none present.
Flue outlet pipe complies with limits given / code and is sealed waterproof.
Combustion air meets requirements (internal, under floor).
Fan speed set is correct.
Burner pressure is correct.
Mounting pad/platform complies with requirements / codes.
D
UCTWORK
All ductwork is completed to plan, correctly supported and airtight, with no bend less than 1.5 x
the ductwork diameter.
Air distribution checked, dampers are adjusted and all outlets correctly adjusted and wiped
clean.
All roof penetrations are fully sealed and watertight.
Man-hole cover replaced.
S
ITE
All rubbish has been removed from inside and on the roof.
C
USTOMER
H
AND
O
VER
The operation of the Thermostat Wall Control.
Operation of zones (where fitted) and air outlets.
Maintenance & service requirements.