DC Interconnections to the Automatic Transfer Switch
Two control wires are required between the A.T.S. panel and the
generator control terminal box. Depending on the distance, 14 to
16 gauge stranded wire should be used. These wires should be
labeled S1 and S23.
****************
***** WARNING *****
****************
Be sure Engine Generator is in the "OFF" position before you
make any DC interconnections.
*******CAUTION******
Never run the AC and DC wiring in the same conduit.
Zenith ATS
The terminal markings in the Zenith ATS are marked “X1” and
“X2”. The wire labeled “Start 1” is routed to start contact "X1” and
the wire labeled “Start 23” is routed to start contact “X2”
ASCO 165 UL SWITCH
Your DC connection points in the ASCO 165 ATS are
terminals “4” and “5 on the interface terminal block.
ASCO 300 UL SWITCH
Your DC connection points in the ASCO 300 ATS are terminals
“14” and “15”. Depending on the size of the switch they are
located in different locations. See next page:
ENGINE CONTROL PANEL
LAYOUT
A. USB PROGRAMMING PORT - USB port for computer
interface. Used for programming the DSE7310 controller.
B. DSE7310 CONTROLLER - See controller explanation on
follow page.
C. Emergency Stop Switch - When depressed this switch will
disconnect all the 12 volt power to the DSE7310 shutting the
engine down. The display on the controller will annunciate
“Emergency Stop”.
X1
X2