PAGE 9

3315-10

60706-165

ASCO 165 UL SWITCH

Your DC connection points in the ASCO 165 UL ATS are

on the terminal block in the upper right hand corner of the
ATS panel. The terminal block is numbered 1 through 9.
You will be using terminals 4 and 5, wire Start 23 will
connect to terminal #5 and wire Start 1 will connect to
terminal #4. See page 15 for a connection diagram.

SETTING THE EXERCISER CLOCK
WINCO Non-UL Only

SEE THE MANUAL SHIPPED WITH THE UL

ATS PANELS FOR THE PROPER PROCE-
DURE FOR SETTING THE WEEKLY
EXERCISE PROGRAMS ON ALL UL
SWITCHES.

Setting the current time and date.

1.

Position the top right hand (RUN) slide switch to the

left position.

2.

Push the clock’s “Day Select Button” until the clock

displays a triangle under the number corresponding to
the current day of the week. (Monday is day 1, Sunday is
day 7)

3.

Push the “Hour Select Button” until the display

indicates the correct time in hours. Note: In the afternoon
you should push the button until a “P” is displayed
beside the correct hour.

4.

Push the “Minute Select Button” until the display

indicates the correct time in minutes.

5.

Position the top right hand (RUN) slide switch to the

center position. The correct time and date should now
be displayed.

Setting the Exerciser Program:

1.

Position the top right hand (RUN) slide switch to the

right hand position.

2.

Position the top left hand (AUTO) slide switch to the

center position.

3.

Press the “Program Select Button” until No. 1 is

displayed on the clock to the right of the time.

4.

Push the “Day Select Button” to select the day you

want the engine generator set to start up and run. Note:
You can get more than one triangle displayed on the
clock. If this happens just keep pressing the button and it
will work back through the cycle and display only one
triangle under whichever day you desire.

5.

With the “Hour” and “Minute” buttons select the time

of day you want the engine to start up.

6.

Press the “Program Select Button” until No. 2 is

displayed on the clock.

7.

Push the “Day Select Button” to select the day you

want the engine to stop. This must be the same day you
selected in step 4 above.

8.

With the “Hour” and “Minute” buttons, select the time

you want the engine to stop. It is recommended you let
the engine run at least 15 minutes during any exercise
period.

9.

Position the top right hand (RUN) slide switch to the

center (RUN) position.

CLOCK NOTES:

This seven day exerciser clock has seven additional

program cycles available. Always keep in mind the odd
number turns the unit on and the even number shuts the
unit off. (i.e. (3 on, 4 off) (5 on, 6 off) etc.)

The relay in the clock will not work unless the transfer

switch is installed and powered up. The relay needs 120
volts AC to operate.

If, when you finish programming the clock, you get an

“EEEE” on the display, it stands for error. The most
common error is that the day of operation has not been
properly set at each step or a program has been turned
on and not turned off. (i.e. programs not properly grouped
1& 2, 3 & 4, 5 & 6, etc.)

On the face of clock is a small button marked “R”, this

is a reset switch. Depressing this switch will remove all
programming in the clock including the time, Use a
small screwdriver or the tip of a pencil to depress this
button. This should be used only as a last resort.

INITIAL START UP

*************
***** WARNING *****
*************
DO NOT jump start these engine generator sets. Starting
these units on a low battery or jump starting them will
cause damage to the engine control module.

Use the following check list to verify correct installa-

tion before starting the engine:

F

Engine oil.* Check level & fill as required with
proper grade/qty.

F

Unit mounting base properly bolted down.

F

Clearance for service and maintenance on all
sides.

F

Proper fuel line material, and size.

F

All fuel line connections tight.

F

Fuel line protected and a moisture trap installed
(may be required for N.G.).

F

LP/NG pressure O.K. 4-6 Oz. (7-11" WC).

F

Battery connections clean and tight.

F

Battery fully charged.

F

All A.C. and D.C. wiring installed and properly
protected.
* Refer to engine owners manual for proper
levels and type.

After completing the above checklist, the engine-

generator set is ready for the initial start-up test.