ION: Bypass jumpers are provided on each output to allow testing and to protect the modules during

CAUT
installation. The jumper shorts the L and SW terminals so that the load circuit is energized when
is on.

the branch breaker

NOTE: Do not remove the bypass jumper until all feed and load wiring has been completed, and the circuits
have been tested for electrical faults.

NOTE: Use copper conductors only – rated 75

°C.

Wire

ORQUE STRIP

LENGTH

Gauge and Torque Values

TERMINAL CONNECTOR

MAX

WIRE RANGE

T

L AND N INPUTS

26-10 AWG

5.31 lb-in (0.6 Nm) to
7.08 lb-in (0.8 Nm) max

3/8”
(9 mm)

SW OUTPUTS

26-10 AWG

5.31 lb-in (0.6 Nm) to
7.08 lb-in (0.8 Nm) max

3/8”
(9 mm)

GROUND LUG

14-4 AWG

25-45 lb-in
(2.8-5.1 Nm)

3/4"
(19 mm)

Load Wiring for GLXP-HSW8 and GLXP-HSW12

TO NEUTRAL*

TO BRANCH BREAKER

TO LOAD

JUMPER

L

CIRCUIT BREAKER (20A MAX)

NEUTRAL

BUS

TO LOADS

N

L

GROUND LUG

N1

L1

SW1

SERVICE

SCREWDRIVER

* A single NEUTRAL connection is required for each module.

1. Test the circuit for electrical faults by turning on each circuit breaker, checking that the breakers do not

trip, and that power is delivered to the proper loads.

2. Turn off the circuit breaker(s) and remove all jumpers.

3. Turn on the circuit breakers.