beautypg.com

Vermont castings ewf36a, Canadian requirements for insulation shield, Continue installing pipe to complete run – Vermont Casting EWF36A User Manual

Page 13: Chimney supports, Additional ceilings, Penetrating the roof, Locate chimney centerpoint on roof, Cut and frame roof hole

background image

13

Vermont Castings EWF36A

20005167

If the area above the ceiling is not an attic, position the
firestop spacer with the flange on the ceiling side and
the angled portion extending up into the hole.
If the area above the ceiling is an attic, position the
firestop spacer with the flange on the top of the framed
hole and the angled portion extending down into the
hole.
Firestop spacers are not available for, nor are they
required on vertical walls.
DO NOT put any sealant around the area where the
outer pipe slides through the firestop spacer. If you seal
this area, it may cause a fire hazard.

Canadian Requirements

for Insulation Shield

In Canada, an attic insulation shield is required to
prevent attic insulaiton from contacxting the chimney
section. Framing dimensions fr the chimney hole should
measure 17¹⁄₂” x 17¹⁄₂” (445mm x 445mm). An attic
shield MUST be installed on top of attic joists (above
the floor level). (Fig. 18)

NOTE: In the U.S., it is a good idea, although not al-
ways required, to install an attic insulation shield where
blown-in insulation is planned to be used in the atic.

Continue Installing Pipe to Complete Run

Continue attaching pipe sections to complete system
to next level always being careful that the pipe is firmly
snapped locked in place before proceeding to next pipe
section.

Chimney Supports

If chimney supports are required, they are installed the
same as elbows. Nail chimney support straps to adja-
cent structural framing, as shown on Figure 16. Bend
straps as necessary and make sure they are secure so
they will support the weight of the chimney. A chimney
support is 2¹⁄₂" (64mm) long when installed. Consider
this dimension when determining how many straight
chimney sections are needed.
NOTE: Chimney supports are generally used in long
runs in a chase installation.

Additional Ceilings

If you encounter additional ceilings, repeat same steps
required for first ceiling installation. See firestop illustra-
tion in Figure 17.

Penetrating the Roof

Run pipe to roofline. Since chimney system must be
vented to the out-of-doors, you must use an approved
CFM Corporation termination.
If a chase is used, refer to the installation manual pro-
vided with the termination cap.

Locate Chimney Centerpoint on Roof

Use same procedure detailed in locating center point of
the flue system.
Drive a nail up through roof at the center point. This will
determine center point on outside of the roof.

Cut and Frame Roof Hole

Size of roof hole varies with the type of chimney ter-
mination installed. Refer to installation instructions
provided with CFM Corporation chimney termination to
find correct size of roof hole.
There must be a 2” (51mm) air space between out-
ermost portion of chimney sections and any adjacent
combustible surfaces. (Combustible surfaces include

IGF263

MBUF

5/9/96

Attic Insulation

Shield

Nails

(4 Required)

Attic Joist

Ceiling

Base

Flanges

FP263

Fig. 18 Attic shield installation (Canadian requirement).

Nails (4)

Attic Installation

Joist

Firestop Spacer

Joist

Firestop Spacer

Nails (4)

Ceiling Installation

FP593

Fig. 17 Firestop spacer installations.

FP593

SR/C

11/20/97