Before Installation
2
Amico Architectural
Note: Do not install studs unless
dimension ’A has been confirmed
by the Amico team
Rough Opening to accommodate
Amico Panel Wall Unit
IMPORTANT: READ AND UNDERSTAND ALL INSTRUCTIONS BEFORE COMMENCING WORK!
Prior to Start of Any On-Site Preparations
All site preparations must be completed prior to the delivery of the panel wall units. Please contact Amico to confirm and
review all information listed below. Failure to do so may result in discrepancies/misalignments during installation.
a. Wall Rough opening dimension, see Figure 1.
b. Stud gauge and size.
c. Wall thickness (e.g. including drywall and any additional paneling mounted on the finished wall).
d. Rough-in locations.
e. Blocking locations, if applicable.
f. Shipping restrictions.
NOTE: Ceiling grid must be installed after the middle section is installed and the rails are attached to the
units.
IMPORTANT: ALL ABOVE INFORMATION MUST BE COORDINATED, CONFIRMED AND APPROVED WITH
AMICO PRIOR TO ANY ON-SITE PREPARATION IN THE AREA WHERE THE HEADWALL WILL BE INSTALLED.
Figure 1 – Rough Opening
Building Studs
on site by others
Dimension ‘A’ to
be confirmed during
final submittal