Bunn espress, Es•2c, Installation – Bunn ES.2C User Manual
Page 5: Plumbing, Electrical, Initial fill & heat
BUNN
Espress
®
ES•2C
™
5
PLUMBING
Install the brewer as indicated below
INSTALLATION
WATER STRAINER
ASSY.
INLET HOSE
BUNN
90 psig max operating pressure
BOM Strainer
FLOW
From Water Treatment
24682.0000
Adaptor
24684.0000
Sealing Washer
23820.0000
Strainer Assy.
24684.0000
Sealing Washer
24683.0000
Adapter
To Espresso Brewer
Inlet Hose
FROM
WATER
SUPPLY
ELECTRICAL
CAUTION-The brewer must be disconnected from the power source until specified. Improper electrical
installation will damage electronic components.
1. Using a voltmeter, check the voltage and color coding of each conductor at the electrical source.
2. When instructed to proceed, connect the brewer to the power source.
CAUTION-The brewer must be properly grounded. A plumbing line will not provide an adequate ground.
INITIAL FILL & HEAT
CAUTION-The brewer must be disconnected from the power source until specified. Improper electrical
installation will damage electronic components. Plumbing must be connected to the brewer before
proceeding.
1. Watch the tank water level gage and push the tank/boiler manual fill button. Hold the button until the water
level is visible in the sight gage.
2. Connect the brewer to the power source.
3. Place the main power switch in the “ON” position. The automatic refill function of the electronic control
system will engage at this time. The refill indicator will glow and the tank will automatically fill with water.
This switch also initiates the heating of the water in the tank/boiler.
4. Press the continuous flow button on each of the group control panels just until water flows from the group
heads. This will purge air from the lines and allow faster heating of the group heads.