4.12 SHUT DOWN AND PARK
NOTE: When parking battery powered units overnight, batteries
should be charged in accordance with instructions in
Section 2 to ensure readiness for following workday.
NOTE: Electric machines are equipped with a static strap due to
static electricity build-ups. Strap is located under rear of
machine chassis.
To shut down and park the machine, the procedures are as
follows:
1. Drive machine to a reasonably well protected area.
2. Ensure boom is lowered over rear drive axle.
3. Shut down Emergency Stop at Platform Controls.
4. Shut down Emergency Stop at Ground Controls. Posi-
tion Platform/Ground Select switch to center OFF.
5. If necessary, cover Platform Controls to protect instruc-
tion placards, warning decals and operating controls
from hostile environment.
4.13 MACHINE LIFTING AND TIE DOWN
Lifting
1. Call JLG Industries, see machine’s serial number plate,
or weigh the individual unit to obtain GVW.
2. Place the boom in the stowed position.
3. Remove all loose items from the machine.
4. Properly adjust the rigging to prevent damage to the
machine and so the machine remains level.
Tie Down
1. Place the boom in the stowed position.
2. Remove all loose items from the machine.
3. Secure the chassis and the platform using straps or
chains of adequate strength.