4.1
Installation Tools Required
The following tools are required to install the circuit breaker panel:
• Screwdrivers (both Phillips and flatblade)
• Torque screwdriver calibrated in pound-force inches or Newton meters
• 3/8-inch and 7/16-inch bits (for torque screwdriver)
• Wire cutter
• Wire stripper
• Compression lug crimper
• Multimeter
• Heat gun
4.2
Materials Required
The following materials are required to install the circuit breaker panel:
• Insulated copper wire for input and output power wires (see
Appendix A
)
• Heat-shrink tubing
• Multimeter
4.3
Pre-Installation Testing
Each circuit breaker panel is thoroughly tested at the ADC factory before being shipped.
However, before the panel is installed, continuity tests should be performed to verify that no
internal damage has occurred during shipping and handling.
Using a multimeter that is set to perform a continuity check, perform the following tests.