Gorman-Rupp Pumps PAH6A60-6090H 1487547 and up User Manual
Page 47
OM-06447
PAH SERIES
MAINTENANCE & REPAIR
PAGE E - 25
adjusting screws so the holes in the collars for the
locking screws align approximately with the holes
in the suction head.
Loosen the back cover nuts used to press the
suction head into the pump casing one full turn.
Pull the collars off the adjusting screws, index them
three detents counterclockwise, and reinstall the
collars on the adjusting screws. Use the collars to
turn the adjusting screws clockwise until the holes
in the locking collars realign with the tapped screw
holes in the back cover plate. Secure the locking
collars to the back cover plate with the hardware
(14 and 15). Install the two remaining back cover
nuts snugly against the adjusting screws.
Remove the first two back cover nuts from their
studs. Turn the adjusting screws clockwise until
they engage the pump casing. Install the locking
collars and hardware (14 and 15). Reinstall the
back cover nuts.
Be sure the wear ring does not scrape against the
impeller when the shaft is turned.
After the face clearance has been set, tighten the
hardware securing the rotating assembly to the
pump casing.
Discharge Check Valve Reassembly and
Installation
(Figure 4)
If the discharge check valve (12) was disas
sembled to replace the flapper or cover O‐ring,
position the flapper in the valve body and check to
ensure free movement.
Install the valve cover O‐ring and secure the cover
to the body with the previously removed hardware.
Apply a small amount of light grease to the dis
charge flange gasket to hold it in place and posi
tion it against the pump casing flange. Support the
discharge check valve assembly using a sling and
a suitable lifting device. Using the previously re
moved hardware, secure the discharge check
valve assembly and flange gasket to the pump as
sembly (1). Secure the discharge check valve to its
support bracket using the previously removed
hardware.
Priming Chamber Assembly and Installation
(Figure 8)
Clean and inspect the components of the priming
valve (1). Inspect the linkage and ensure the orifice
button (not shown) squarely engages the valve
seat. Replace the orifice button if required (see
Priming Chamber Removal and Disassembly
for orifice button removal).
If the orifice button was removed, screw the new
orifice button into the linkage bar until fully seated.
Align the hole in the linkage bar with the holes in the
bracket and reinstall the pivot pin. Secure the pivot
pin with the previously removed “e‐clip”.
Adjust the orifice button seating as necessary by
screwing the orifice button into or out of the linkage
bar. Proper adjustment is achieved when the ori
fice button fully seats against the orifice before the
linkage bar on the float bottoms against the
threads on the orifice button. When adjustment is
complete, install and tighten the lock washer and
hex nut securing the orifice button.
Install the strainer (6) and priming valve gasket (4).
Lower the float into the priming chamber (5) and
secure the priming valve with the previously re
moved hardware (2 and 3).
(Figure 7)
Install the baffle and gasket (8 and 9) and use a
sling and suitable lifting device to position the prim
ing chamber assembly on the pump suction spool
(7, Figure 4). Secure the priming chamber assem
bly with the hardware (6 and 7).
Reconnect both the suction piping and the air dis
charge tubing to the priming chamber assembly.
LUBRICATION
Seal Assembly
(Figure 6)
Before starting the pump, remove the vented plug
(13) and fill the seal cavity with approximately 170
ounces (5 liters) of SAE No. 30 non‐detergent oil to
the center of the sight gauge (10). Clean and rein
stall the vented plug. Check the oil level regularly
and maintain it at the middle of the sight gauge.
Bearings
(Figure 6)
The bearing housing was fully lubricated when
shipped from the factory. Check the oil level regu