10 SERIES
OM-02146
MAINTENANCE & REPAIR
PAGE E - 10
should be just tight enough to seal the back cover
shoulder.
Suction Check Valve Installation
Inspect the check valve components and replace
as required. Subassemble the check valve weights
(53 and 57) and check valve gasket (56) using the
attaching hardware (54 and 55).
Position the check valve assembly (52) on the tabs
on the check valve seat (67) with the large weight
toward the inside of the pump casing. Install the in
ner check valve gasket (60) on the studs (50).
Position the check valve assembly and seat in the
suction port. Install the outer check valve gasket
(59) and suction flange (58). Secure the complete
assembly with the nuts (51). Check the operation
of the check valve to ensure proper seating and
free movement.
Final Pump Assembly
Secure the pump to the base with the previously re
moved hardware. Connect the power source. Be
sure to reinstall any leveling shims used under the
pump mounting feet.
Be sure the pump and power source are securely
mounted to the base.
Install the suction and discharge lines and open all
valves. Make certain that all piping connections are
tight, properly supported and secure. Open all the
valves in the suction and discharge lines.
Be sure the pump and power source have been
properly lubricated, see LUBRICATION.
Remove the fill plug assembly (6) and fill the pump
casing with clean liquid. Reinstall the fill plug and
tighten it.
Refer to OPERATION, Section C, before putting
the pump back into service.
LUBRICATION
Bearings
The pedestal was fully lubricated when shipped
from the factory. Check the oil level regularly
through the sight gauge (26) and maintain it at the
middle of the gauge. When lubrication is required,
add SAE No. 30 non‐detergent oil through the hole
for the air vent (14). Do not over‐lubricate. Over‐lu
brication can cause the bearings to over‐heat, re
sulting in premature bearing failure.
Under normal conditions, drain the pedestal once
each year and refill with clean oil to the middle of
the sight gauge. Change the oil more frequently if
the pump is operated continuously or installed in
an environment with rapid temperature change.
Monitor the condition of the bearing lubri
cant regularly for evidence of rust or mois
ture condensation. This is especially im
portant in areas where variable hot and
cold temperatures are common.
For cold weather operation, consult the factory or a
lubricant supplier for the recommended grade of
oil.
Seal Assembly
The seal assembly is lubricated by the medium be
ing pumped. No additional lubrication is required.
Power Source
Consult the literature supplied with the power
source, or contact your local power source repre
sentative.