APPENDIX A
GENERAL – FINAL CHECK LIST
___ 1. Is the unit base properly leveled, grouted and
secured?
___ 2. Are all lubrication points properly lubricated?
___ 4. Is the shut-off valve to the pump suction open?
___ 5. Is the shut-off valve on the discharge line open?
___ 6. Is the piping properly supported so as to pre-
vent strains on unit?
___ 7. Is the distribution system purged of debris and
air? Is the system filled?
___ 8. Are the pump and driver shafts properly
aligned?
___ 9. Is the pump rotation correct?
___ 10. Is there adequate ventilation and air circulation?
___ 11. Have all piping connections been made? Have
all flanged joints been checked for tightness?
___ 12. Has an automatic air release valve been
installed on the top of the casing of each hori-
zontal split case pump?
___ 13. Are remote alarm and control panels connected
and in operation as required by NFPA 20?
___ 14. Are pump bearings properly lubricated?
___ 15. Is coupling properly lubricated, if required?
DIESEL INSTALLATION – FINAL CHECK LIST
ELECTRIC DRIVEN INSTALLATION – FINAL CHECK LIST
___ 1. Have all electrical connections been made bet-
ween engine terminal block and the controller?
___ 2. Has engine cooling system been filled with 50%
water and 50% antifreeze solution?
___ 3. Has diesel fuel supply tank been properly
installed in accordance with the requirements of
NFPA 20? Has vent pipe been installed?
___ 4. Have both fuel ‘supply’ and ‘return’ connections
been made to fuel tank?
___ 5. Has fuel tank been filled with No. 2 diesel fuel?
___ 6. Has oil been added to the engine crankcase as
per diesel manufacturer’s recommendations?
___ 7. Does air cleaner require servicing?
___ 8. Has proper power been supplied to the diesel
controller of adequate amperage as recom-
mended by the controller manufacturer?
___ 9. Have batteries been installed, serviced and cables
connected? Are the batteries fully charged?
___ 10. Has proper power been supplied to the diesel
water jacket heater of adequate amperage and
voltage as recommended by the diesel
manufacturer?
___ 1. Has the casing relief valve been installed
between the pump discharge and check valve?
___ 2. Are proper electrical connections made to the
control panel and motor (proper voltage and
adequate size)?
CAUTION: Stuffing Box Damage may occur. Do
not run pumps dry. Fill and vent the pump volute
prior to operation. FAILURE TO FOLLOW THESE
INSTRUCTIONS COULD RESULT IN PROPERTY
DAMAGE AND/OR MODERATE PERSONAL
INJURY.
DANGER: Charge batteries in a well-ventilated
area. FAILURE TO FOLLOW THESE INSTRUC-
TIONS WILL RESULT IN SERIOUS PERSONAL
INJURY, DEATH, AND/OR PROPERTY DAMAGE.
CAUTION: Do not connect power until diesel
engine is filled with coolant or the heater may
burnout. FAILURE TO FOLLOW THESE INSTRUC-
TIONS COULD RESULT IN PROPERTY DAMAGE
AND/OR MODERATE PERSONAL INJURY.
WARNING: Rotating shafts can catch loose
clothing. Do not operate the pump without all
guards in place. FAILURE TO FOLLOW THESE
INSTRUCTIONS WILL RESULT IN SERIOUS PER-
SONAL INJURY, DEATH, AND/OR PROPERTY
DAMAGE.