Flashing installation, Chapter 4 flashing installation, Grain systems formed flashing installation – Grain Systems Bin Flooring PNEG-216 User Manual

Page 11

background image

PNEG-216 24' Cor-Lok and Cut-Lok Flooring

11

4. Flashing Installation

Figure 4A

Grain Systems Formed Flashing Installation

If a bin sweep auger will be used, overlap flashing so that the sweep with climb up on to the next flashing
section when rotating (usually clockwise).

(See Figure 4A.)

This will prevent the rotating/slipping outer

wheel of the sweep from catching on the flashing edges. (All GSI power sweeps and carry-in sweeps
manufactured after April 2002 run clockwise.)

After floor is in place, place 1-1/4" bolts through pre-punched holes in sidewall. Bolt heads should be on
outside of bin.

See Figure 4B

to determine the correct sequence for placing the nuts and washers. Finger

tighten the nuts until all flashing is installed, then go back and fully tighten. While holding the flashing flat
and pushing in towards the bin wall, fasten the flashing to the floor with two sheet metal screws.

Figure 4B