Installation, Shroud installation, Aeration adjustment – Waterford Appliances NATURAL GAS E61-LP User Manual
Page 12
12
Waterford E61 Gas Fireplace Insert
INSTALLATION
SHROUD
INSTALLATION
1) Attach the 2 side Surround Panels to the
body. Each side panel attaches to the body
with two bolts per side (top and bottom) and
use a washer and a 1/2" spacer with each
screw.
2) Plug the 'quick connect' electrical connec-
tion into the junction box. An alternative
wire outlet is provided on the junction box
so that the blower power cable can be
routed out the back of the shroud if so
desired.
Alternate
wiring port
Top Surround Panel
Retaining Bracket
Side panel with
1/2" spacer
Rear View: Side
panel attached
with 2 bolts.
AERATION
ADJUSTMENT
The burner aeration is factory set but may need
adjusting due to either the local gas supply, air
supply or altitude.
with 38,000 Btu with 27,000 (NG) /
29,000 LP
Natural Gas Natural Gas
3/16"(4.75mm)
1/8"(3.18mm)
Propane Propane
1/4"(6.35mm)
3/16" (4.75mm)
1) Turn the heater off and allow it to cool.
2) Open the bottom door.
Closed - Tall yellow flame
Open - Short blue flame
Allen Key
3) To adjust the aeration: use the allen key to
turn the turning gear which will adjust the
air shutter. Open the air shutter for a blue
flame or close it for a yellower flame.
Valve Description
1) Gas cock knob
2) Manual high/low adjustment
3) Pilot Adjustment
4) Thermocouple Connection
5) Main Operator
6) Outlet Pressure Tap (Manifold Pressure)
7) Inlet Pressure Tap (Supply Pressure)
8) Pilot Outlet
9) Main Gas Outlet
10) Flange Securing Screw Holes
11) Alternative TC Connection Point
12) Thermoelectric Unit
13) Additional Valve Mounting Hole
4) Restart the heater and let it burn for approx-
imately 15 minutes. Repeat until the desired
flame appearance is achieve.
Caution: Carbon will be produced if the
air shutter is closed too much.
Note: Any damage due to carboning re-
sulting from improperly setting
the aeration controls is NOT cov-
ered under warranty.
Note: Aeration Adjustment should only
be performed by an authorized
Regency Installer at the time of
installation or service.
3) Connect the Hob to the Top Surround Panel.
The Hob is attached with 2 bolts (with
washers) on either side.
4) The Hob & Top Surround Panel will be placed
in position as the last step of the installation.
The flue spillage test and fitting the draft
hood are more easily accomplished without
the Hob & Top Surround Panel in position.
When ready to install the Hob & Top Sur-
round Assembly, lower it down onto the top
of the body. It is held in place by its own
weight and the retaining brackets on each
side.
O v e r s i z e
Shroud Only: The
4 retaining brack-
ets on the Top Sur-
round must be re-
moved and rotated
180
o
and replaced.
The end of the
bracket must ex-
tend beyond the
bottom of the Top
Surround.