beautypg.com

4 generator tests under load, 5 checking automatic operation, 6 adjusting the regulator (natural gas only) – Bryant Automatic Standby Generator ASPAS1BBA007 User Manual

Page 7

background image

1.4

GENERATOR TESTS UNDER LOAD

To test the generator set with electrical loads applied,

proceed as follows:
1. Set generator’s main circuit breaker to its OFF (or

OPEN) position.

2. Turn OFF all loads connected to the transfer switch

terminals T1 and T2.

3. Set the generator's AUTO/OFF/MANUAL switch to

OFF.

4. Turn OFF the utility power supply to the transfer

switch, using the means provided (such as a utility

main line circuit breaker).

Do not attempt manual transfer switch
operation until all power voltage supplies to
the transfer switch have been positively turned
off. Failure to turn off all power voltage
supplies will result in extremely hazardous and
possibly fatal electrical shock.

5. Manually set the transfer switch to the STANDBY

position, i.e., load terminals connected to the

generator's E1/E2 terminals. The transfer switch

operating lever should be down.

6. Set the generator's AUTO/OFF/MANUAL switch to

MANUAL. The engine should crank and start

immediately.

7. Let the engine stabilize and warm up for a few

minutes.

8. Set the generator’s main circuit breaker to its ON (or

closed) position. Loads are now powered by the

standby generator.

9. Turn ON electrical loads connected to transfer switch

T1 and T2. Apply an electrical load equal to the full

rated wattage/amperage capacity of the installed

generator.

10. Connect an accurate AC voltmeter and a frequency

meter across terminal lugs E1 and E2. Voltage

should be greater than 230 volts; frequency should

be greater than 58 Hertz.

11. Let the generator run at full rated load for 20-30

minutes. Listen for unusual noises, vibration or other

indications of abnormal operation. Check for oil

leaks, evidence of overheating, etc.

12. When testing under load is complete, turn OFF

electrical loads.

13. Set the generator's main circuit breaker to its OFF (or

OPEN) position.

14. Let the engine run at no-load for a few minutes.
15. Set the AUTO/OFF/MANUAL switch to OFF. The

engine should shut down.

1.5

CHECKING AUTOMATIC
OPERATION

To check the system for proper automatic operation,

proceed as follows:
1. Set generator’s main circuit breaker to its OFF (or

OPEN) position.

2. Check that the AUTO/OFF/MANUAL switch is set to

OFF.

3. Turn OFF the utility power supply to the transfer

switch, using means provided (such as a utility main

line circuit breaker).

4. Manually set the transfer switch to the UTILITY

position, i.e., load terminals connected to the utility

power source side.

5. Turn ON the utility power supply to the transfer

switch, using the means provided (such as a utility

main line circuit breaker).

6. Set the AUTO/OFF/MANUAL switch to AUTO. The

system is now ready for automatic operation.

7. Turn OFF the utility power supply to the transfer

switch.

With the AUTO/OFF/MANUAL switch at AUTO, the

engine should crank and start when the utility source

power is turned OFF. After starting, the transfer switch

should connect load circuits to the standby side. Let the

system go through its entire automatic sequence of

operation.
With the generator running and loads powered by

generator AC output, turn ON the utility power supply to

the transfer switch. The following should occur:
• After about six seconds, the switch should transfer

loads back to the utility power source.

• About one minute after retransfer, the engine should

shut down.

1.6

ADJUSTING THE REGULATOR
(NATURAL GAS ONLY)

Although the generator has been factory set to provide

maximum power, it may be necessary in some areas to

adjust this setting. Because natural gas has different BTU

or power content across the country the engine may not

perform as designed.
If experiencing engine problems at high or full load

conditions follow these steps. It will require a frequency

meter to perform this procedure.
1. Turn off utility power to the main distribution panel in

the house. This can be done by switching the service

main breaker to the off or open position.

2. Allow the generator to start. Before loading the

generator, confirm that the No Load Frequency, with

the top open and front panel off, is set to 63-63.5 Hz.

Transfer load to emergency circuits.

Section 1 — Post Installation Start-up and Adjustments

Bryant Air-cooled 7 kW, 12 kW and 15 kW Generators

Bryant

5