Beijer Electronics iX T10A EN User Manual
Page 10
Installation
4. Connect the cables in the specified order, according to the drawing and steps
below.
Caution:
•
Ensure that the operator panel and the controller system have the same electrical
grounding (reference voltage level), otherwise errors in communication may
occur.
•
The operator panel must be brought to ambient temperature before it is started
up. If condensation forms, ensure that the operator panel is dry before connecting
it to the power outlet.
•
Ensure that the voltage and polarity of the power source is correct.
•
Use only shielded communication cables.
•
Separate high voltage cables from signal and supply cables.
24V DC
RS232/
RS422/
RS485
24V DC
A
D
Controller
Power
B
Ethernet
C
–
Connect cable A.
–
Connect cable B, using an M5 screw and a grounding conductor (as short
as possible) with a cross-section of minimum 2.5 mm
2
.
–
Connect cable C.
–
Connect cable D. The recommended cross-section of the cable is
1.5 mm
2
.
5. Carefully remove the laminated film over the operator panel display, to avoid
static electricity that could damage the panel.
Note:
Only for iX T10A panels with part number 630000301:
When connecting the operator panel to the power outlet for the first time, make
sure not to interrupt power for a minimum of 48 hours in order to charge the battery
completely. After that, the battery may be charged partly during a shorter period of
time.
Beijer Electronics, MAEN017F
10