beautypg.com

E-port commissioning, Decommissioning an e-port, Recommissioning an e-port – Brocade Network Advisor Port Commissioning Quick Start Guide (Supporting Network Advisor 12.3.0) User Manual

Page 13

background image

Brocade Network Advisor Port Commissioning Quick Start Guide

13 of 21

Publication Number: 53-1003220-01

E-Port commissioning

Although you can use any of the following methods to access the E-Port commissioning commands, individual
procedures only include one method.

From the main menu, select the E-Port in the Product List or Topology, then select Configure > Port
Commissioning > Decommission/Recommission > Port.

From the Product List, right-click the E-Port and select Decommission/Recommission > Port.

From the Topology, right-click the E-Port and select Decommission/Recommission > Port.

From a Dashboard widget, right-click the E-Port and select Decommission/Recommission > Port.

Decommissioning an E-Port

NOTE

You must enable Lossless DLS on both the source and destination switches before you decommission an E-Port.

NOTE

Fabric tracking must be enabled (refer to Brocade Network Advisor User Manual

“Enabling fabric tracking”

on

page 289) to maintain the decommissioned port details (such as port type, device port WWN, and so on). Do not
accept changes in the Management application client.

Select the E-Port in the Product List, then select Configure > Port Commissioning > Decommission > Port.

While decommissioning is in progress, a down arrow icon displays next to the port icon in the Product List. The port
decommissioning status (Port Decommission in Progress or Decommissioned E Port) displays in the Additional Port
Info field of the Product List. You can view the port commissioning results in the deployment reports (refer to

“Viewing a port commissioning deployment report”

on page 18).

When the decommission is complete, an application event displays in the Master Log detailing success or failure.

Recommissioning an E-Port

NOTE

You do not need to enable Lossless DLS before you recommission an E-Port.

Select the E-Port in the Product List, then select Configure > Port Commissioning > Recommission > Port.

While recommissioning is in progress, an up arrow icon displays next to the port icon in the Product List. The port
recommissioning status (Port Recommission in Progress or Recommissioned E Port) displays in the Additional Port
Info field of the Product List. You can view the port commissioning results in the deployment reports (refer to

“Generating a deployment report”

on page 1709).

When the recommission is complete, an application event displays in the Master Log detailing success or failure.