4.1 Start-Up
74
YASKAWA TM.iQp.06 iQpump Controller User Manual
4.1
Start-Up
In order to provide the most reliable iQpump drive available and to avoid any extra costs related to loss or reduction of warranty
coverage, an authorized Yaskawa service representative should complete this start-up procedure. Please complete the following checklist
and maintain it in a secure location as technical service personnel may request information from this checklist.
◆ Drive Start Up Preparation
Date:____________________________________________
Start-Up Person:
Company Name:_________________________________
Start-Up Location: _________________________________
Sales Order #: ___________________________________
Serial #: _________________________________________
Printed Name: ___________________________________
Drive Location: ___________________________________
Phone #: _______________________________________
Signature: _______________________________________
Owner’s Representative:
Printed Name: ___________________________________
Phone #: _________________________________________
Company: ______________________________________
Signature: ________________________________________
Step
1. The iQpump drive is thoroughly tested at the factory. The start up person should verify that the iQpump drive is free of shipping
and installation damage. Shipping damage is not covered by the Yaskawa warranty. Claims must be filed with the shipping
company as soon as possible for any potential recovery via insurance.
2. Review the iQpump Drive User Manual (TM.iQp.06) shipped with the iQpump drive.
3. Verify that the model number and voltage ratings in the purchase order match the nameplate data for each unit.
4. Location of the iQpump drive is important to achieve proper performance and normal operating life. The unit should be installed
in an area where it is protected from:
Direct sunlight, rain or moisture
Corrosive gases or liquids
Vibration, airborne dust or metallic particles
5. Ensure the iQpump drive is on a vertical surface with adequate space for air circulation (4.75” above and below, 1.2” on each
side). Refer to
6. Verify that the proper branch circuit protection is installed in front of the iQpump drive. Refer to
for proper input fuse or circuit breaker sizing.
7. Avoid running input and output wiring in the same conduit.
8. Avoid routing power wiring near equipment sensitive to electrical noise.