Page 50

Battery Preventive Maintenance Procedure

The purpose of the preventive maintenance is to ensure that the battery is in good, working
condition. The observations, measurements, and tests performed are designed to determine
the “state of health” of the battery. It will also allow for the prediction of future performance and
preempt possible failure.

1. Measure the float charge voltage.

a. At the power bay bus.
b. At the battery.
c. Reset voltage if necessary.

2. Measure the float current on each battery cable. If it is fluctuating, measure maximum

and minimum.

3. Measure the ac ripple voltage at the battery.
4. Measure the float voltage of each cell or monoblock. Record the battery memory location

allocated on the battery tester.

5. Perform a load test on each cell or monoblock and measure the internal cell resistance

and inter-cell resistance of each cell or monoblock.

6. Ensure that all protective covers are replaced and that the battery is electrically non-

hazardous to personnel that could be working in the vicinity

7.4. Final Inspection:

5. Verify that the interior and exterior of the system is clean and free from debris.
6. Ensure all wires connected and bolts are properly tightened.
7. Ensure the following the User, Service, and Calibration parameters are set properly on

the controller (default settings are in parenthesis):
LVD
LVD1

Trip

LVD1

Reset

Battery Parameters
Discharge

Threshold

Float

Voltage

Maximum

Recharge

Compensation

Method

8. Verify on the status menu that the system is functioning correctly with no alarms.
9. Be sure to leave the site as orderly and neat as possible.