AT-EN646MOD Installation Guide
Chapter 3: Enclosure Installation
25
Splice the Drop Cable and Securing the Fusion Splice Tray
1. Locate the fusion splice tray (single-part plastic) and the fiber splice clip in the accessory kit.
2. Select the size of the fiber slice clip you are using (2mm for blue or 3 mm for black).
3. Trim off a 4-section piece and snap this into the splice tray, as shown in Figure 20.
Figure 20. Inserting fiber splice clip
4. Decide where to begin the wire run on the splice tray and in which direction the wire will go around the
splice tray.
Note
In most cases, as shown in the example, the wire should run from the upper left corner and go
clockwise.
5. Center the splice tray over the pegboard holes in the enclosure.
6. From the accessory kit, remove the two 8mm screws, and attach the splice tray.
7. Mock up the fiber layout to determine the length of optical wire to use. Wrap the optical wire (at this
point the buffer tube) 2 times around the tray, starting with the upper left corner and ending at the top
center. Cut the fiber beyond this 2 loop point.