beautypg.com

Control wiring – APC DC Power Plant MX28B-1200 User Manual

Page 25

background image

Revision B

MX28B-1200 PRODUCT MANUAL

MX28B-1200/2400

19

5.6.2 Control Wiring

Cables for controlling and monitoring the rectifiers and circuit breakers/fuses must be run from
expansion frames to the control unit in the base frame. There are three basic cables used for
these functions:

•= The AWA-0970 ten-pin ribbon cable connector handles serial communications for rectifier

reporting and control. This cable connects to the J1 connector of the DC/DC converter
PCB’s (EAA-0111) in each power box frame.

•= Circuit breaker reporting in extension power and distribution bays is communicated back to

the control unit through the AWA-0972 cable. This cable is connected to J15 on the control
unit interface PCB in the base unit and runs to connector J2 on the Alarm Extension PCB
(EAA-0072) in the remote bay. Additional bays are connected via the same cable, which
connects up to four Alarm Extension PCB’s.

•= Fuse reporting is routed from the Fuse Sense PCB (ADV-1204) to the control unit via cable

AWA-0967.

Refer to Figure 5-6 for a pictorial representation of multi-bay cable connection. Figure 5-7
shows the information as a wiring diagram.

This manual is related to the following products: