Transferring from Generator Power to Utility Power:

1.

On the Power Center, turn OFF Generator MAIN breaker and turn ON Utility MAIN breaker. On 200 amps Main breaker models, this will require sliding the
interlock mechanism up with the left hand while turning ON the 200 amp circuit breaker.

2.

Turn ON any branch circuit breakers in the Power Center and Main Load center that are OFF.

3.

Shut down the generator, following the procedures in the generator Owner’s Manual.

4.

Unplug the power cord from the Power Center and then the generator.

5.

Let the generator cool down before storing in a dry, secured location.

6.

To ensure that your generator will work properly when you need it, it is important to start and run your generator under load regularly and keep the tank
filled with fresh fuel. Perform the above steps at least ONCE A MONTH to keep the generator properly “exercised.”

TABLE 2 - Wire Connector Usage Chart:

WIRE SIZE

12

10

8

6

14

Red NA NA NA

12

Red Red NA NA

10

NA Red NA NA

8

NA NA Blue

Blue

6

NA NA Blue

Blue


TABLE 3 – Compatible Circuit Breaker Types:

Compatible GFCI, Arc-Fault/ Surge Protection Circuit Breakers:

♦ Siemens QP, QT, QPH, HQP, QPF, QPHF, QFP, QE, QEH

♦ Siemens: QPF (GFCI), QAF (Arc Fault), QP (Surge Protector)

♦ Cutler Hammer/Westinghouse Series BD, BR, BQ, GFC
♦ Challenger Type A, C, HAGF
♦ Square D Series HOM
♦ GE Series THQL

WIRING DIAGRAMS:




























Gen/Tran Corporation

P.O. Box 1001, Alpharetta, GA 30009-1001

Toll Free: 1-888-GEN-TRAN Fax: 770-552-7756

www.gen-tran.com

© 2003 Gen-Tran Corporation. All Rights Reserved. PowerStay is a trademark of Gen-Tran Corporation

PN XXXXX Rev A 6-12-03

This manual is related to the following products: